Day 2: 7/17/14
Helpers: Amanda, Nin_j, Myles, Coomerae, Gorilla, Fyre, and me (Vyriss).
Progress: We finished the glass part and put in the walls to the lobby and flooring. We also put in the floor to the 2nd and almost done the 3rd floor.
Plan for tomorrow: To try to finish all the floors.
How long the meeting took: 2 hours.
Thank you guys for the support and the help and thank you lily for the donation! And I like to thank my helpers too! I would not be this far without them!
-Vyriss
*The picture that is named Looking up that is the picture looking upwards from the halfway done 3rd floor*
Helpers: Amanda, Nin_j, Myles, Coomerae, Gorilla, Fyre, and me (Vyriss).
Progress: We finished the glass part and put in the walls to the lobby and flooring. We also put in the floor to the 2nd and almost done the 3rd floor.
Plan for tomorrow: To try to finish all the floors.
How long the meeting took: 2 hours.